Question: A software project comprises the following activities, whose time estimates are given against each other as below: Activity Estimated Duration (weeks) - Optimistic Most Likely
A software project comprises the following activities, whose time estimates are given against each other as below:
| Activity | Estimated Duration (weeks) | ||
| - | Optimistic | Most Likely | Pessimistic |
| 1-2 | 3 | 6 | 15 |
| 1-3 | 2 | 5 | 14 |
| 1-4 | 6 | 12 | 30 |
| 2-5 | 2 | 5 | 8 |
| 2-6 | 5 | 11 | 17 |
| 3-6 | 3 | 6 | 15 |
| 4-7 | 3 | 9 | 27 |
| 5-7 | 1 | 4 | 7 |
| 6-7 | 4 | 19 | 28 |
Question:
a) Find the critical path for the project.
b) Whatis the expected project duration?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts