Question: A software project comprises the following activities, whose time estimates are given against each other as below: Activity Estimated Duration (weeks) - Optimistic Most Likely

A software project comprises the following activities, whose time estimates are given against each other as below:

Activity Estimated Duration (weeks)
- Optimistic Most Likely Pessimistic
1-2 3 6 15
1-3 2 5 14
1-4 6 12 30
2-5 2 5 8
2-6 5 11 17
3-6 3 6 15
4-7 3 9 27
5-7 1 4 7
6-7 4 19 28

Question:

a) Find the critical path for the project.

b) Whatis the expected project duration?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!