Question: A project consists of three tasks A, B and C. Project Manager assigned the tasks A and B to Saeed and task C to Ahmed
- A project consists of three tasks A, B and C.
- Project Manager assigned the tasks A and B to Saeed and task C to Ahmed
- Project Managers estimate is that task A and C require 30 hours of work each and task B requires 10 hours of work
- Project Manager assigns the tasks to be completed in two weeks.
- After two weeks, Saeed reports that it took him 40 hours to complete 80% of task A and 50% of tasks B. Ahmed reports that it took him 40 hours to complete tasks C.
- Whats projects cost and schedule variance?