Question: Based on the information provided in Project Assignment Data.pdf file, answer the rest of questions. 5. For activity H Attach the door, what is/are the
Based on the information provided in Project Assignment Data.pdf file, answer the rest of questions.

5. For activity H Attach the door, what is/are the predecessor(s)? Choose all that apply.
Draw your project network diagram based on the information provided. Based on your network diagram, what is (are) the successor node(s) for activity E? Choose all that apply.
What is the earliest project completion time in minutes? Assume that the project starts right away (0 minute). Round to the nearest integer.
What is the EST of activity E? Round to the nearest integer.
Working backwards on the latest times (using the project completion time found in question 7), what is the LST of activity E? Round to the nearest integer
What is the slack time for activity E? Round to the nearest integer.
What are the critical activities (with zero slack time) for this project? Choose all that apply.
According to the crashing data provided. If you want to decrease the total assembly time by 1 minute, which task/tasks are you going to crash? Choose all that apply.
The management of Cabinets Unlimited wants to know how long it will take to assemble a new cabinet in their product line. To that end, the Production Manager has identified the following tasks (and task times) that must be accomplished: Task Description Immediate Predecessor A B Task time (minutes) 10 5 15 D E F G Prepare the wheels Mount the wheels Assemble the sides Attach the top Attach the base Insert the brackets Insert the shelves Attach the doors Attach the back Paint the unit 11 10 5 5 H 9 9 15 J The wheels are mounted after they are prepared. The base cannot be attached until the sides are assembled and the wheels are mounted. The top cannot be attached nor the brackets inserted until the sides are assembled. The shelves are inserted after the brackets are installed. The back is attached after the base and top are attached. The doors are attached after the shelves are inserted and the top and base are attached. The unit is painted after the back and doors are attached. To prepare for the possible project expediting, crash data has been collected as below. (Crash time is the minimum time that can be achieved for each task - tip: it is what you can do and you do not have to crash to the minimum.) Task A B. Normal time 10 5. Crash Cost per Minute 2 Crash Time 8 5 12 8 8 4 15 11 4 10 2 5 3 4 D E F G H I J 5 3 2 9 9 15 6 8 15Step by Step Solution
There are 3 Steps involved in it