Question: A project engineer has created an AON diagram for the relocation of the Styrofoam production facility, which is presented below. Please determine: a . The

A project engineer has created an AON diagram for the relocation of the Styrofoam production facility, which is presented below. Please determine:
a. The critical path of the project.
b. The slack time between the various pathways
c. The earliest start time and earliest finish time for activity F.
d. If $2000? week is assigned to crash activity E, if $4000 is spent to crash, what is the impact to reducing the length of the project?