Question: A project expected completion time is 58 days with standard deviation of 4. a) What is the probability of finishing the project in exactly 58

A project expected completion time is 58 days

A project expected completion time is 58 days with standard deviation of 4. a) What is the probability of finishing the project in exactly 58 days? b) With probability of 98%, how long is the project completion time? c) What is the probability of finishing the project in less than 64 days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!