Question: A Project has $ 5 0 0 , 0 0 0 in Planned Value. Current SPI is 0 . 9 0 . You have a
A Project has $ in Planned Value. Current SPI is You have a positive cost variance of $ What is the Earned Value and the Actual Cost at this point in the project? Must show all calculations