Question: Given the following for a 12 month project, answer the questions that follow. (Total - 10 points) Planned Value (PV) = $50,000 Rate of Performance

Given the following for a 12 month project, answer the questions that follow. (Total - 10 points)

Planned Value (PV) = $50,000 Rate of Performance (RP) = 80% Actual Cost (AC) = $48,000 Budget at Completion (BAC) = $500,000 Estimated Time to Complete the project is 12 months.

  1. What is the cost variance (CV), schedule variance (SV) , cost performance index (CPI) and schedule performance index (SPI) of the project.? (5 points)
  2. How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget? Explain your answers. (2)
  3. Calculate the estimate at completion (EAC) for the project based on the above noted information. Is the project performing better or worse than planned (budget)? (2)
  4. Estimate how long it will take to finish this project at the current rate of performance? (1 point)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!