Question: A project has a critical path with activities A , B , and C . Activity A has a duration of 6 days, Activity B

A project has a critical path with activities A, B, and C. Activity A has a duration of 6 days, Activity B has a duration of 10 days, and Activity C has a duration of 8 days. The crash cost for Activity A is $1500 per day, for Activity B is $2000 per day, and for Activity C is $1800 per day. If you need to crash the project by 3 days, what is the most cost-effective way to do it?