Question: A project s critical path has activities A , B , and C with durations of 5 , 1 0 , and 1 5 days,

A projects critical path has activities A, B, and C with durations of 5,10, and 15 days, respectively. Crashing activity C by 3 days costs $9,000, while crashing activity B by 5 days costs $8,000. Which activity should be crashed first to minimize cost while reducing the project duration?
Activity C
Activity A
Activity B
Both B and C should be crashed simultaneously