Question: A project s critical path has activities A , B , and C with durations of 5 , 1 0 , and 1 5 days,
A projects critical path has activities A B and C with durations of and days, respectively. Crashing activity C by days costs $ while crashing activity B by days costs $ Which activity should be crashed first to minimize cost while reducing the project duration?
Activity C
Activity A
Activity B
Both B and C should be crashed simultaneously