Question: A project has a critical path with an expected duration of 22 and variance of 14. What is the probability it will be completed within
A project has a critical path with an expected duration of 22 and variance of 14. What is the probability it will be completed within 20-25 weeks (inclusive)? (the range of the answers account for rounding errors)
Group of answer choices
Between 55% and 58%
Between 17% and 20%
Between 47% and 52%
Between 64% and 67%
Between 60% and 63%