Question: A project has a schedule performance index (SPI) = 0.6 and cost performance index (CPI) = 1.1. Which of the following is true? Select one:

A project has a schedule performance index (SPI) = 0.6 and cost performance index (CPI) = 1.1. Which of the following is true?

Select one:

a.

The project is progressing well

b.

The project is ahead of schedule and over budget

c.

The project is behind schedule and under budget

d.

The project is ahead of schedule and under budget