Question: A Project has adopted Earned Value Method for the management of cost. The forecasted duration of the Project is 10 months and the following cumulative

A Project has adopted Earned Value Method for the management of cost. The forecasted duration of the Project is 10 months and the following cumulative planned value (PV) of project cost are available:

End of Month 1 2 3 4 5 6 7 8 9 10
Cumulative PV (000)/Rs. 100 200 300 400 500 600 700 800 900 1000

At end of Month 5 the actual cost of the project was Rs 575 000 and 55 % of the project was completed. Determine EV, CV, SV, CPI, SPI and EAC for this project. Assume that for this project cost performance will not change in the future.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!