Question: A project has an Earned Value ( EV ) of $ 6 0 0 , 0 0 0 , an Actual Cost ( AC )
A project has an Earned Value EV of $ an Actual Cost AC of $ and a Budget at Completion TBC of $ The project manager predicts the remaining work will require an additional $ What is the new Estimate at Completion EAC and Variance at Completion VAC
EAC $ VAC $
EAC $ VAC $
EAC $ VAC $
EAC $ VAC $
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
