Question: A project has an Earned Value ( EV ) of $ 6 0 0 , 0 0 0 , an Actual Cost ( AC )

A project has an Earned Value (EV) of $600,000, an Actual Cost (AC) of $750,000, and a Budget at Completion (TBC) of $1,000,000. The project manager predicts the remaining work will require an additional $400,000. What is the new Estimate at Completion (EAC) and Variance at Completion (VAC)?
EAC = $1,250,000, VAC =-$250,000
EAC = $1,200,000, VAC =-$200,000
EAC = $1,150,000, VAC =-$150,000
EAC = $1,350,000, VAC =-$350,000

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!