Question: A project has been estimated to take six weeks and cost $120,000. Cost and percent complete data are provided below: Task $/Task Week 1 Week

A project has been estimated to take six weeks and cost $120,000. Cost and percent complete data are provided below:

Task $/Task Week 1 Week 2 Week 3 Week 4 Week 5
A $20,000 100% 100% 100% 100% 100%
B $10,000 100% 100% 100% 100%
C $25,000 75% 100% 100% 100%
D 25,000 40% 80% 100%
E 10,000 40% 100% 100%
F 10,000 30% 80%
G $5,000 40% 100% 100%
H 15,000 40%
ACWP 6,500 $23,000 54,000 80,000 90,000

Fill in the Earned Value table above to show PV, EV, AC, the cost variance (CV) and Schedule variance (SV) at each week through and including week 5.

What is your interpretation of this cost data?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!