Question: A project has four activities (A, B, C, and D) that must be performed sequentially. The probability distributions for the time required to complete each

A project has four activities (A, B, C, and D) that must be performed sequentially. The probability distributions for the time required to complete each of the activities are as follows:

Activity Activity Time (weeks) Probability
A 4 0.28
5 0.39
6 0.22
7 0.11
B 8 0.20
10 0.53
12 0.27
C 12 0.09
14 0.23
16 0.40
18 0.24
20 0.04
D 10 0.64
12 0.36

A. Provide the base-case, worst-case, and best-case calculations for the time to complete the project.

Activity Base case Worst case Best case
A fill in the blank 1 weeks fill in the blank 2 weeks fill in the blank 3 weeks
B fill in the blank 4 weeks fill in the blank 5 weeks fill in the blank 6 weeks
C fill in the blank 7 weeks fill in the blank 8 weeks fill in the blank 9 weeks
D fill in the blank 10 weeks fill in the blank 11 weeks fill in the blank 12 weeks
Total fill in the blank 13 weeks fill in the blank 14 weeks fill in the blank 15 weeksB

B. Use the random numbers 0.8644, 0.1417, 0.101 and 0.2516 to simulate the completion time of the project in weeks.

Activity Random Number Completion Time
A 0.8644 fill in the blank 16 weeks
B 0.1417 fill in the blank 17 weeks
C 0.101 fill in the blank 18 weeks
D 0.2516 fill in the blank 19 weeks
Total fill in the blank 20 weeks

C. Discuss how simulation could be used to estimate the probability that the project can be completed in weeks or less. Simulation provides a distribution of project completion times. The (mean/percentage) of times weeks and under can be used to estimate the probability that the project will be completed within weeks.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!