Question: A project has four activities. Activity A has no predecessors and a duration of 1 week. Activity B has Activity A as its predecessor and
A project has four activities. Activity A has no predecessors and a duration of 1 week. Activity B has Activity A as its predecessor and a duration of 4 weeks. Activity C has Activity A as its predecessor and a duration of 3 weeks. Activity D has activities B and C as its predecessors and a duration of 2 weeks. What is the critical path for this project?
A) A,C,D
B) A, C
C) A,B,D
D) Cannot be determined
All of the following are objectives of supply management EXCEPT this:
A)Search for and develop as many suppliers as possible
B) Purchase the required goods and services at the lowest total cost of ownership
C)Ensure the required level of purchased item quality
D)Seek ways to improve the organizations competitive position
Which department provides projections for sales that are used as input to the forecasting process?
A) Field Sales
B) Distribution
C) Supply Management
D) Operations
Automation and standardized procedures are often used to?
A) Increase process variability
B) Neither increase nor decrease process variability
C) Decrease process variability
D) Both increase and decrease process variability
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts