Question: A project has four activities. Activity A has no predecessors and a duration of 1 week. Activity B has Activity A as its predecessor and

 A project has four activities. Activity A has no predecessors and
a duration of 1 week. Activity B has Activity A as its

A project has four activities. Activity A has no predecessors and a duration of 1 week. Activity B has Activity A as its predecessor and a duration of 4 weeks. Activity (3 has Activity A as its predecessor and a duration of 3 weeks. Activity D has activities B and C as its predecessors and a duration of 2 weeks. What is the critical path for this project