Question: A project has just completed its 87 th item in the project plan. It was scheduled to have spent $300,000at this point in the plan,
A project has just completed its 87th item in the project plan. It was scheduled to have spent $300,000at this point in the plan, but has actually spent only $250,000. The project manager estimates that the value of the work actually finished is nearly $200,000.What are the spending and schedule variances for the project? What are the SPI and CPI?What is the Critical Ratio?
a.CV =
b.SV =
c.SPI =
d.CPI =
e.CR =
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
