Question: A project has just completed its 87 th item in the project plan. It was scheduled to have spent $300,000at this point in the plan,

A project has just completed its 87th item in the project plan. It was scheduled to have spent $300,000at this point in the plan, but has actually spent only $250,000. The project manager estimates that the value of the work actually finished is nearly $200,000.What are the spending and schedule variances for the project? What are the SPI and CPI?What is the Critical Ratio?

a.CV =

b.SV =

c.SPI =

d.CPI =

e.CR =

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Law Questions!