Question: A project has multiple paths with activity C having no slack and a daily crash cost of $250 and activity Q having a slack of
A project has multiple paths with activity C having no slack and a daily crash cost of $250 and activity Q having a slack of 2 and a crash cost of $50 per day. Which of the following is false?
Group of answer choices
The critical path is the is the path with the longest length.
It is better to crash activity Q before activity C.
The project can have multiple critical paths if the all have the same path length
When crashing, once a path is critical, it will still critical through all crashing
Crashing includes the concept of the time value of money