Question: A project has multiple paths with activity C having no slack and a daily crash cost of $250 and activity Q having a slack of

A project has multiple paths with activity C

A project has multiple paths with activity C having no slack and a daily crash cost of $250 and activity Q having a slack of 2 and a crash cost of $50 per day. Which of the following is false? The critical path is the is the path with the longest length. It is better to crash activity Q before activity C. The project can have multiple critical paths if the all have the same path length When crashing, once a path is critical, it will still critical through all crashing Crashing includes the concept of the time value of money