Question: A project has six tasks. The following table shows the task time and the dependencies among the tasks. Find the critical path. . Show all
- A project has six tasks. The following table shows the task time and the dependencies among the tasks. Find the critical path.
. Show all work.
| Task Number# | Time (days) | Predecessors |
| 1 | 3 | |
| 2 | 15 | 1 |
| 3 | 13 | 2 |
| 4 | 11 | 2 |
| 5 | 5 | 4 |
| 6 | 8 | 3,5 |
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock