Question: 8. (15 Points) A project has six tasks. The following table shows the task time and the dependencies among the tasks. Find the critical path.

8. (15 Points) A project has six tasks. The following table shows the task time and the dependencies among the tasks. Find the critical path. Show all work. Task Number# Time (days) Predecessors 1 3 2 15 1 3 13 2 4 11 2 5 5 4 6 8 3,5