Question: A project has the activity duration and cost information indicated in the table where all times are in weeks. What is the total cost for

A project has the activity duration and cost information indicated in the table where all times are in weeks. What is the total cost for completing this project in 40 days?

Activity Predecessor Normal Time Normal Cost Crash Time Crash Cost
A -- 8 $12,000 5 $22,000
B A 12 $18,000 9 $32,000
C A 15 $22,000 9 $62,000
D B 3 $9,000 2 $18,000
E C 9 $15,000 5 $35,000
F E 7 $5,000 5 $8,000
G D 8 $13,000 6 $23,000
H A 12 $20,000 8 $32,000
J H 6 $45,000 4 $56,000

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!