Question: A project has the activity duration and cost information indicated in the table where all times are in weeks. What is the total cost for
A project has the activity duration and cost information indicated in the table where all times are in weeks. What is the total cost for completing this project in 40 days?
| Activity | Predecessor | Normal Time | Normal Cost | Crash Time | Crash Cost |
| A | -- | 8 | $12,000 | 5 | $22,000 |
| B | A | 12 | $18,000 | 9 | $32,000 |
| C | A | 15 | $22,000 | 9 | $62,000 |
| D | B | 3 | $9,000 | 2 | $18,000 |
| E | C | 9 | $15,000 | 5 | $35,000 |
| F | E | 7 | $5,000 | 5 | $8,000 |
| G | D | 8 | $13,000 | 6 | $23,000 |
| H | A | 12 | $20,000 | 8 | $32,000 |
| J | H | 6 | $45,000 | 4 | $56,000 |