Question: A project has the activity duration and cost information indicated in the table where all times are in weeks. There is a penalty of $
A project has the activity duration and cost information indicated in the table where all times are in weeks. There is a penalty of $ per week for every week the project extends beyond weeks. What is the cost of the least expensive project possible?
Activity Normal time Crash time Normal Cost Crash Cost Predecessor
A $
B A
C A
D B
E B
F C D
G E F