Question: A project has the activity duration and cost information indicated in the table where all times are in weeks. There is a penalty of $

A project has the activity duration and cost information indicated in the table where all times are in weeks. There is a penalty of $250 per week for every week the project extends beyond 32 weeks. What is the cost of the least expensive project possible?
Activity Normal time Crash time Normal Cost Crash Cost Predecessor
A 85 $1,0002,000
B 641,5002,000 A
C 851,8002,300 A
D 1291,0001,800 B
E 14119501,450 B
F 971,5001,900 C, D
G 752,3002,800 E, F
Answers:
$14,450
$13,450.
Correct $12,450
$11,450

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!