Question: A project has the activity duration and cost information indicated in the table where all times are in weeks. What is the total cost for
A project has the activity duration and cost information indicated in the table where all times are in weeks. What is the total cost for completing this project as quickly as possible?
| Activity | Predecessor | Normal Time | Normal Cost | Crash Time | Crash Cost |
| A | -- | 8 | $12,000 | 5 | $22,000 |
| B | A | 12 | $18,000 | 9 | $32,000 |
| C | A | 15 | $22,000 | 9 | $62,000 |
| D | B | 3 | $9,000 | 2 | $18,000 |
| E | C | 9 | $15,000 | 5 | $35,000 |
| F | E | 7 | $5,000 | 5 | $8,000 |
| G | D | 8 | $13,000 | 6 | $23,000 |
| H | A | 12 | $20,000 | 8 | $32,000 |
| J | H | 6 | $45,000 | 4 | $56,000 |
Select one:
a.
$258,333
b.
$244,000
c.
$255,600
d.
$262,000
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock