Question: A project has the activity duration and cost information indicated in the table where all times are in weeks. What is the total cost for

A project has the activity duration and cost information indicated in the table where all times are in weeks. What is the total cost for completing this project as quickly as possible?
Activity
Predecessor
Normal Time
Normal Cost
Crash Time
Crash Cost
A
--
8
$12,000
5
$22,000
B
A
12
$18,000
9
$32,000
C
A
15
$22,000
9
$62,000
D
B
3
$9,000
2
$18,000
E
C
9
$15,000
5
$35,000
F
E
7
$5,000
5
$8,000
G
D
8
$13,000
6
$23,000
H
A
12
$20,000
8
$32,000
J
H
6
$45,000
4
$56,000
Group of answer choices
$258,333
$255,600
$262,000
$244,000

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!