Question: a project has the activity duration and cost information indicated in the table . there is penalty of 250$ per month for every month the
a project has the activity duration and cost information indicated in the table . there is penalty of 250$ per month for every month the project extends beyond 9 months
a) draw the network diagram and find the project completion time. what is the project completion itime in months
b) which one is critical path? ( acef, adg, bcef, abdg)
c) which activity should be crashed to complete the project in 14 months?
d) what is the total cost of completing the project in 14 months
e) what is the lowest total cost for completinf this project
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
