Question: A project has the following activities: a. A project has the following activities: Normal Normal Crash Crash Immediate Time Cost Time Cost Activity Predecessors (wee
A project has the following activities:

a. A project has the following activities: Normal Normal Crash Crash Immediate Time Cost Time Cost Activity Predecessors (wee Draw the network diagram based on normal time.
b. What are potential paths and corresponding durations?
c. What is the expected project completion time based on normal time?
d. What is the most economical way and how much will it cost to reduce the completion time of the project by three weeks?
Please write legibly/show work. Thank you.
2. A project has the following activities: Normal Normal Crash Crash Immediate Time Cost Time Cost Activity Predecessors (weeks) ($) (weeks) ($) A none 4 3,000 3 5,000 B 9 5,000 7 8,000 A 4 7,000 4 7,000 D B, C 6 6,000 4 8,000 E 8 4,000 6 8,000 F D 3 4,000 2 9,000 G E, F 4 2,000 N 2 7,000Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock