A project has the following activities and their durations: Normal Time Crash Time Normal Cost Crash...
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
A project has the following activities and their durations: Normal Time Crash Time Normal Cost Crash Cost Activity Preceding Activity (RM '000) (RM '000) 3 8 (days) (days) 1 A 3 B 1 1 6 D A, B 2 9 9 E B 4 16 20 F 6 9 12 D 4 13 18 E, F, G The overhead cost is RM 200 per day. 7 12 15 (a) On a normal basis, draw an activity-on-arc network diagram. Label your network with the activity, duration, earliest event time and latest event time for each of the activities. (6 marks) (b) Determine the critical path and minimum time required to complete the project. (2 marks) (c) The company has limited number of men available to work on the project. Only two activities can be under way at the same time. Will this delay the project when compared to the time that unlimited resources would have been? Explain your (4 marks) answer. (d) The customer would like the project to be completed in 12 days and imposes a penalty of RM 1000 per day for excess time over 12 days, with a bonus RM 500 per day for earlier completion. Suppose activities cannot be crashed partly, show the network on timescale at each step by crashing appropriate activities in proper order. What is your recommendation(s) to the project manager if he would like to minimize the total project cost? (8 marks) 223 424 A project has the following activities and their durations: Normal Time Crash Time Normal Cost Crash Cost Activity Preceding Activity (RM '000) (RM '000) 3 8 (days) (days) 1 A 3 B 1 1 6 D A, B 2 9 9 E B 4 16 20 F 6 9 12 D 4 13 18 E, F, G The overhead cost is RM 200 per day. 7 12 15 (a) On a normal basis, draw an activity-on-arc network diagram. Label your network with the activity, duration, earliest event time and latest event time for each of the activities. (6 marks) (b) Determine the critical path and minimum time required to complete the project. (2 marks) (c) The company has limited number of men available to work on the project. Only two activities can be under way at the same time. Will this delay the project when compared to the time that unlimited resources would have been? Explain your (4 marks) answer. (d) The customer would like the project to be completed in 12 days and imposes a penalty of RM 1000 per day for excess time over 12 days, with a bonus RM 500 per day for earlier completion. Suppose activities cannot be crashed partly, show the network on timescale at each step by crashing appropriate activities in proper order. What is your recommendation(s) to the project manager if he would like to minimize the total project cost? (8 marks) 223 424
Expert Answer:
Posted Date:
Students also viewed these accounting questions
-
A new project has the following forecasts: Initial Outlay .......... $ 40,000 Life of project ........... 5 yrs Net annual cash flow ..... $ 15, 000 Expected rate of return ....... 10%
-
A project has the following forecasted cash flows: The estimated project beta is 1.5. The market return r m ? is 16 percent, and the risk-free rate r f ? is 7 percent. a. Estimate the opportunity...
-
A project has the following cash flows: This project requires two outflows at Years 0 and 2, but the remaining cash flows are positive. Its WACC is 10%, and its MIRR is 14.14%. What is the Year 2...
-
Some rocks or bricks contain small air pockets in them and have a spongy structure. Assuming the air spaces form columns of an average diameter of 0.006 mm, determine how high water can rise in such...
-
Under the same assumptions as the previous problem, show that the value of a claim paying S2(T ) if S1(T) > KS2(T ) is where 2, 1, and 2 are defined as in the previous problem. In the next set of...
-
Hill Fine Instruments manufactures trumpets, trombones, tubas, and other brass instruments. The following standards were developed for a line of trumpets: During April, Hill scheduled 550 trumpets...
-
What are the basic elements of a use case diagram?
-
Write an address book program that stores your contacts' names and their email addresses. The names and email addresses are originally stored in a file called phonebook.in, in the format: Harry...
-
Provide References In September of 2015, the EPA issued Volkswagen ( OTCPK:VLKAY ) a notice of violation of the Clean Air Act of 1963. The EPA accused the Volkswagen Group of intentionally...
-
Which series has the highest beta. BraveNewCoin Liquid Index for Bitcoin 1D BNC Trading Brave Ne Yellow Green Blue Orange
-
The site "College Simply" gives the following information about Pacific Lutheran University graduates: "Six years after enrolling, alumni who are working have average earnings of $37,200 per year"...
-
What features of the political process make effective development policymaking so difficult?
-
Describe briefly the essential assumptions and major features of the Todaro model of rural-urban migration. One of the most significant implications of this model is the paradoxical conclusion that...
-
What critical issues are raised from the examination of development problems and prospects facing Brazil?
-
In the context of development priorities, what are the relative roles of central banks, commercial banks, development banks, informal and unorganized sources of credit, and microfinance such as the...
-
Distinguish carefully between private and social benefits and costs of education. What economic factors give rise to the wide divergence between private and social benefit-to-cost valuations in most...
-
What strength magnetic field is needed to hold antiprotons, moving at 5.00x10 7 m/s in a circular path 2.00 m in radius? Antiprotons have the same mass as protons but the opposite (negative) charge.
-
A Firm intends to invest some capital for a period of 15 years; the Firm's Management considers three Options, each consisting of purchasing a machinery of a specific brand, different for each...
-
Key success factors. Dalworth Construction Company provides construction services for major projects. Managers at the company believe that construction is a people-management business, and they list...
-
Describe the five-step decision-making process.
-
How do management accountants support strategic decisions?
Wings Of Wonder The Monarch Butterflys Incredible Journey 1st Edition - ISBN: B0CKYBSKQK - Free Book
Study smarter with the SolutionInn App