Question: A project has the following activities and durations: Activity A ( 3 days ) Activity B ( 4 days ) Activity C ( 2 days

A project has the following activities and durations: Activity A (3 days) Activity B (4 days) Activity C (2 days) Activity A Activity D (5 days) Activity E (6 days) Activity C and Activity E converge into the final milestone Draw the network diagram, determine the critical path, and calculate the project completion time.