Question: A project has the following Activities, Predecessors ; and Durations: Activity| Immediate Predecessors |DURATION (WEEKS) A - 2 | B - 3 |C - 4,|
A project has the following Activities, Predecessors ; and Durations: Activity| Immediate Predecessors |DURATION (WEEKS)
A - 2 | B - 3 |C - 4,| D A,B 6| E B,C 8| F C 10| G E,F 2| H D 15 |I G 2
1 Draw the 'Activity on Node' network diagram. (10)
2 Identify all notations used in the backward and forward path (10)
3 Identify all slack times (5)
4 Identify the Critical Path (5)