Question: A project has the following Activities, Predecessors ; and Durations: Activity| Immediate Predecessors |DURATION (WEEKS) A - 2 | B - 3 |C - 4,|

A project has the following Activities, Predecessors ; and Durations: Activity| Immediate Predecessors |DURATION (WEEKS)

A - 2 | B - 3 |C - 4,| D A,B 6| E B,C 8| F C 10| G E,F 2| H D 15 |I G 2

1 Draw the 'Activity on Node' network diagram. (10)

2 Identify all notations used in the backward and forward path (10)

3 Identify all slack times (5)

4 Identify the Critical Path (5)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!