Question: A project has the following activities, with specified precedents, expected durations (in days), and crash cost/day. Each activity can be crashed to a minimum

A project has the following activities, with specified precedents, expected durations (in

A project has the following activities, with specified precedents, expected durations (in days), and crash cost/day. Each activity can be crashed to a minimum duration of 1 day. (This is the same network as a previous problem.) What is the minimum total cost to shorten the project by 2 days? Round your answers to 2 decimals. Activity Precedent Duration Crash cost/day $350 $250 $400 $150 $200 $275 $500 $300 A B E F G H Answer: A A B B D E 3 3.9 6 CO 6 4.2 4 5.8 8

Step by Step Solution

3.42 Rating (161 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

To determine the minimum total cost to shorten the project by 2 days we need to identify the critica... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!