Question: A project has the following attributes: PV = $60 EV = $50 AC = $75 BAC = $100 What is the cost variance (CV) for

A project has the following attributes:

PV = $60

EV = $50

AC = $75

BAC = $100

  1. What is the cost variance (CV) for this project? (5 points)
  2. What is the schedule variance for this project? (5 points)
  3. What is the estimate at completion (EAC) for this project? Assume variances are typical the same rate of spending will continue. Please round your answer to 2 decimal points. (10 points)