Question: For a project, the following earned value data have been assessed: AC: $ 1,000,000 CV: $ -200,000 SPI: 1.12 BaC: $ 4,650,000 What is the

For a project, the following earned value dataFor a project, the following earned value data

For a project, the following earned value data have been assessed: AC: \$ 1,000,000 CV: \$ -200,000 SPI: 1.12 BaC: \$ 4,650,000 What is the earned value of the project? Select one: a. $1,200,000 b. $1,480,000 c. $1,000,000 d. $1,650,000 A project was budgeted at $2,000,000. Meanwhile, the project is executed, and the following current figures have been assessed: PV: $800,000 EV: $750,000 AC: $850,000 Assuming that the cost variance was caused by one-time cost drivers, which are no more effective, what estimate at completion (EaC) can you derive from these figures? Select one: a. $2,222,222 b. $2,000,000 c. $2,100,000 d. $1,900,000

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!