Question: A project has the following progress. [ 2 5 ] Planned project length is 6 months. Project budget is $ 1 , 2 0 0

A project has the following progress. [25]
Planned project length is 6 months.
Project budget is $1,200,000.
Time worked to date is 3 months.
Actual cost to date is $550,000.
Percentage of the planned project to be completed is 50%.
Actual percentage of the project completed is 35%.
Determined the planned value. [4]
Determine the earned value. [4]
Determine the Schedule variance. [4]
What is the schedule performance? [4]
Are we behind or ahead of schedule? [4]
 A project has the following progress. [25] Planned project length is

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!