Question: A project has the following progress. [ 2 5 ] Planned project length is 6 months . Project budget is $ 1 , 2 0

A project has the following progress.
[
2
5
]
Planned project length is
6
months.
Project budget is $
1
,
2
0
0
,
0
0
0
.
Time worked to date is
3
months.
Actual cost to date is $
5
5
0
,
0
0
0
.
Percentage of the planned project to be completed is
5
0
%
.
Actual percentage of the project completed is
3
5
%
.
Determined the planned value.
[
4
]
Determine the earned value.
[
4
]
Determine the Schedule variance.
[
4
]
What is the schedule performance?
[
4
]
Are we behind or ahead of schedule?
[
4
]