Question: A project has the following statistics: A C = $ 5 0 , 0 0 0 , VAC = $ 2 , 5 0 0

A project has the following statistics:
AC=$50,000,VAC=$2,500,ETC=$68,500BAC=$121,000 and EAC=$118,500. What is the forecasted cost to complete this project?
A. $50,000
B. $118,500
C. $121,000
D. $68,500
 A project has the following statistics: AC=$50,000,VAC=$2,500,ETC=$68,500BAC=$121,000 and EAC=$118,500. What is