Question: A project has three critical paths: A-B-C-D-E, A-G- H-E, and A-F-I-E. Crashing costs (in thousands, per week) for each activity is listed below: Activity Crashing

A project has three critical paths: A-B-C-D-E, A-G- H-E, and A-F-I-E. Crashing costs (in thousands, per week) for each activity is listed below: Activity Crashing Crashing Crashing 1st time 2nd time 3rd time A 43 5 3 B 29 3 1 C 3 D 3 2 1 3 2 11 6 18 1 What is the total cost of reducing this project by two weeks? Oa 52 O b. 47 O c. 37 Od 53 85 E F G H Oe. 36 2 42 30 25 2 27 3 28 2 12