Question: A project has three critical paths: A-B-C- D-E, A-G-H-E, and A-F-I-E. Crashing costs in thousands, per week) for each activity is listed below: Activity Crashing

A project has three critical paths: A-B-C- D-E,

A project has three critical paths: A-B-C- D-E, A-G-H-E, and A-F-I-E. Crashing costs in thousands, per week) for each activity is listed below: Activity Crashing Crashing Crashing 1st time 2nd time 3rd time 35 3 4 B 25 1 N C 30 2 2 D 8 11 1 E 41 3 1 F 33 31 4 G G 29 5 4 H 3 6 1 | 3 7 3 What is the total cost of reducing this project by two weeks? O a 44 Ob. 55 Oc. 38 Od 76 O e. 49