Question: A project has three critical paths: A-B-C-D-E, A-G-H-E, and A-F-I-E. Crashing costs (in thousands, per week) for each activity is listed below: Activity Crashing 1st
A project has three critical paths: A-B-C-D-E, A-G-H-E, and A-F-I-E. Crashing costs (in thousands, per week) for each activity is listed below: Activity Crashing 1st time Crashing 2nd time Crashing 3rd time
A 30 2 4
B 26 2 1
C 27 4 1
D 8 11 3
E 29 4 2
F 25 34 1
G 25 32 4
H 5 10 2
I 8 5 1
What is the total cost of reducing this project by two weeks? a. 47 b. 51 c. 50 d. 31 e. 59