Question: A project has three critical paths: A-B-C-D-E, A-G-H-E, and A-F-I-E. Crashing costs (in thousands, per week) for each activity is listed below: Activity Crashing 1st

A project has three critical paths: A-B-C-D-E, A-G-H-E, and A-F-I-E. Crashing costs (in thousands, per week) for each activity is listed below: Activity Crashing 1st time Crashing 2nd time Crashing 3rd time

A 30 2 4

B 26 2 1

C 27 4 1

D 8 11 3

E 29 4 2

F 25 34 1

G 25 32 4

H 5 10 2

I 8 5 1

What is the total cost of reducing this project by two weeks? a. 47 b. 51 c. 50 d. 31 e. 59