Question: 4 A project has three critical paths. A-B-C-D-E, A-G-H-E, and A-F-I-E. Crashing costs (in thousands, per week) for each activity is listed below: Activity Crashing

4 A project has three critical paths. A-B-C-D-E,
4 A project has three critical paths. A-B-C-D-E, A-G-H-E, and A-F-I-E. Crashing costs (in thousands, per week) for each activity is listed below: Activity Crashing 1st time Crashing 2nd time Crashing 3rd time 40 3 2 B 29 3 C 28 3 D 4 2 E 43 2 F 25 33 26 16 3 2 5 7 3 9 NO 4 3 G -N 9 4 What is the total cost of reducing this project by two weeks? a 55 b37 C46 d 52 Oe 83