Question: A project has three parallel paths. A - B - C has a length of 4 5 days. A - D - C has a

A project has three parallel paths. A-B-C has a length of 45 days. A-D-C has a length of 25 days. Finally, E-F has a length of 20 days. What is the expected project completion time?