Question: A project has two critical path activities, X and Y , with durations of 1 0 and 1 5 days, respectively. The cost of crashing
A project has two critical path activities, X and Y with durations of and days, respectively. The cost of crashing X is $ per day, and the cost of crashing Y is $ per day. If the project must be reduced by days overall, and both activities can be crashed equally, what is the minimum additional cost?
$
$
$
$