Question: Among critical path activities A - B - C - E - F - G - H , lowest crash slope is for activity H
Among critical path activities ABCEFGH lowest crash slope is for activity H $ Maximum crashing of hours is possible for activity H So we will first crash activity H by hrs New project duration hours. Crashing cost $ $ Critical path will remain same ABCEFGH
Next activity with lowest crash slope on critical path is activity C $ Maximum crashing of hour is possible for activity C So we will crash activity C by hr New project duration is hours. Crashing cost $ $ $ Critical path will remain same ABCEFGH
Next activity with lowest crash slope on critical path is activity E $ Maximum crashing of hours is possible for activity E So we will crash activity E by hrs New project duration is hours. Crashing cost $ $ $ Critical path will remain same ABCEFG
Next activity with lowest crash slope on critical path is activity B $ Maximum crashing of hour is possible for activity B So we will crash activity B by hr New project duration is hours. Crashing cost $ $ $ Critical path will remain same ABCEFG
Next activity with lowest crash slope on critical path is activity G $ Maximum crashing of hour is possible for activity G So we will crash activity G by hr New project duration is hours. Crashing cost $ $ $ Critical path will remain same ABCEFG
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock