Question: A project involves the following activities, their predecessors, and the times (in weeks) associated with each activity. Activity Predecessor Time (Weeks) A -- 2 B
A project involves the following activities, their predecessors, and the times (in weeks) associated with each activity.
| Activity | Predecessor | Time (Weeks) |
| A | -- | 2 |
| B | -- | 3 |
| C | -- | 4 |
| D | A | 6 |
| E | B | 3 |
| F | B | 5 |
| G | C | 7 |
| H | D,E | 9 |
| I | F,G | 5 |
| J | H,I | 1 |
a. Draw a complete network for the above.
b. Determine the critical path and list all the activities that are on the critical path. What is the expected project completion time?
c. Develop the activity schedule for the project.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts