Question: please use excel 2. A project involves the following activities, their predecessons, and the times (in weeks) associatrd with exch wetwisy a. Draw a complete
2. A project involves the following activities, their predecessons, and the times (in weeks) associatrd with exch wetwisy a. Draw a complete network for the above. b. Determine the critical path and list all the activities that are on the critical path. What is the expected project completion time? c. Develop the activity schedule for the project