Question: A project is at the final development stage. The test lead informs the risk manager that a key feature may not be testable due to
A project is at the final development stage. The test lead informs the risk manager that a key feature may not be testable due to changes in the environment. What should the risk manager do? Confirm the risk triggers are still valid. Review the feature with the project team. Escalate the issue to the project board. Ask the architect to develop acceptance cnteria