A project is expected to generate CFAT of ? 3,56,000. Other data relating to project are as
Fantastic news! We've Found the answer you've been seeking!
Question:
A project is expected to generate CFAT of ? 3,56,000. Other data relating to project are as follows:
Useful life = 6 years.
Risk free rate = 8%
Certainty factor = 0.9
Tax rate = 35%
Initial investment = ? 12,00,000.
Depreciation Method = SLM.
Calculate risk adjusted IRR of the project using rates of 8% & 16%.
(A) 14.62%
(B) 18.51%
(C) 16.47%
(D) 15.49%
Related Book For
Contemporary Financial Management
ISBN: 9780324289114
10th Edition
Authors: James R Mcguigan, R Charles Moyer, William J Kretlow