Question: A project is illustrated by the SPI/CPI graph as shown below. Which of the following describes the status of the project correctly? (Select all that
A project is illustrated by the SPI/CPI graph as shown below. Which of the following describes the status of the project correctly? (Select all that apply)
| The schedule performance has improved for three weeks. | ||
| The schedule performance has worsened for three weeks. | ||
| Based on the trend of the graph, the project is expected to be ahead of schedule at week 4. | ||
| Based on the trend of the graph, the project is expected to be behind schedule at week 4. | ||
| The cost performance has improved for three weeks. |