Question: A project is in its 1 7 th week and has just completed activity H . The total costs to complete the project through activity

A project is in its 17th week and has just completed activity H. The total costs to complete the project through activity H was budgeted as $47,600. According to the project plan, activity H was to be completed by week 18. The actual costs incurred to complete the project through activity H was $52,100. Which of the following statements is true?